Union Point Weymouth New Homes: Why Water Sets the Timeline

October 15, 2026

From January through August 2026, Weymouth recorded 241 single-family closings and 108 condo closings. Out at the former South Weymouth Naval Air Station, the developers of Union Point told Abington officials in September that they have more than 2,500 homes pre-sold on the Weymouth side of the base. That's more than seven times the town's entire resale activity so far this year, all waiting in one place.

Those homes will come, but not on a schedule set by buyers, builders, or zoning. Water sets it. That explains why the Weymouth market you can buy into this fall looks the way it does, and why it's likely to stay that way for a while.

The Gallons Decide Where the Houses Go

The master developers, New England Development and Brookfield Properties, closed on the land on June 30, 2026, after six years of permitting. According to South Shore News' report on the September 8 Abington Select Board meeting, Weymouth has allocated 450,000 gallons per day of municipal water to the project, and municipal law prohibits that water from crossing into Abington or Rockland.

That one restriction shapes the whole site. All current development is confined to Weymouth. Abington's 179-acre share, planned for commercial office space, institutional uses, and over-55 townhomes, is on hold. The developers have signed a preliminary memorandum of understanding to reserve 350,000 gallons per day from the City of Brockton, and they are looking at improvements to existing local wells so Abington doesn't have to wait years.

New England Development's John Twohig put it plainly at that meeting:

"We have over 2,500 homes pre-sold, and that's a combination of multifamily, single-family, townhomes, and over-55 developments... All in Weymouth, because that's the only place we have water."

"Pre-sold" is the developer's own aggregate figure. The reporting doesn't break it down into consumer purchase contracts, named homebuilders, prices, or unit counts by type. So it says a lot about demand for the land. It says much less about when a family could get keys.

What Starts This Fall Is a Road

The work beginning now is groundwork for the houses. Phase 1 is about 1.5 miles of roadway and utility backbone, entirely on the Weymouth side. It realigns Shea Drive behind the Shea Memorial Grove jet display, runs past the Union Point Sports Complex and the former Navy gym, connects into the Delahunt Parkway roundabout, and ends at a temporary turnaround at the Weymouth–Abington line. It carries water, drainage, electric, gas, a stormwater detention basin feeding French's Stream, and two sewer pump stations tied to force mains on Route 18.

The developers said the first contract was awarded in early September, construction would start within two weeks, and active work would run about a year. On September 29, The Patriot Ledger described the redevelopment as "finally taking a major step forward this fall."

The corridor is meant to open up 10 initial development parcels. If the one-year estimate holds, the roads and pipes would be finished around fall 2027. Houses come after that. None of the reporting gives a first-occupancy date.

For neighbors, the construction plan sends heavy trucks through access corridors off Route 18 and Route 228, not residential streets such as Snowbird Avenue and Trotter Drive. The developers have also committed to dust controls, staging yards placed away from homes, and a dedicated project website for detour and schedule updates.

The Pipe Behind the Pipe

That 450,000-gallon allocation is only the near-term supply. The long-term plan is for Weymouth to join the Massachusetts Water Resources Authority, the regional system that serves much of Greater Boston. Here is where that stands, according to MWRA's July 29, 2026 staff update and the town's own notices:

  1. June 2024: The Town of Weymouth and the Southfield Redevelopment Authority submitted a joint state environmental (MEPA) filing to join the MWRA system.
  2. March 2026: A draft environmental impact report was filed. Public comments were due May 8, 2026.
  3. July 29, 2026: MWRA reported the filing was still under review. The request to move water between river basins had been cut from 8.84 million gallons per day to 5.5 million on peak days, about 75% of the roughly 7.5 million gallons of capacity in that part of MWRA's system.
  4. 2031 or 2032: South Shore News reports that the pipeline, a 36-inch line running about seven miles from Quincy and the Blue Hills to Weymouth's Great Pond treatment facility at an estimated cost of more than $100 million, is not expected to operate until then.

The sources describe the volume a little differently. South Shore News describes a line delivering roughly 14 million gallons per day, with 5.5 million set aside for Weymouth and the base. MWRA frames 5.5 million as the transfer being requested. Both agree on the 5.5 figure for Weymouth.

The money is coming in stages too. The town's July 13, 2026 notice says the master developer paid $11,551,500 upfront in water and sewer mitigation fees, out of $30,470,280 that will be paid as development thresholds are reached. The town also received $35 million from the Healey-Driscoll Administration. That money covers a package of work: designing the MWRA pipeline, sewer upsizing on Route 18, a sewer extension to Abington, and transportation improvements at 25 intersections in Weymouth and surrounding towns, among other items. It isn't a check for the pipe alone.

The existing system already has limits. In May 2026, Weymouth adopted Level 1 drought conservation measures for town-water customers, limiting nonessential outdoor watering to one day a week. A town that rations lawn sprinklers in a dry spring is unlikely to hand out much more water before the new pipeline arrives.

Meanwhile, the Market You Can Actually Buy In

Put the timelines together. The roads should be done around late 2027, the pipeline sometime around 2031 or 2032, and houses on a schedule nobody has published. So Union Point isn't adding supply to this fall's market, and it isn't adding to next spring's either. The homes for sale in Weymouth right now are the existing ones. In August 2026, the two halves of that market behaved very differently.

Weymouth, August 2026 Single-family Condo
Closed sales 38 10
Median sale price $674,125 $437,500
Homes for sale at month end 40 27
Months of supply 1.3 2.1
Cumulative days on market until sale 23 50
Percent of original list price received 103.9% 96.0%

These numbers come from the South Shore Realtors August 2026 town report, which uses MLS data provided by the Massachusetts Association of Realtors. A single month can swing on small numbers, so the year-to-date figures help. Through August 2026, the single-family median was $688,500, up 3.7% from the same stretch of 2025. The condo median was $385,000, down 0.8%.

At 1.3 months of supply, a single-family home sells for above its original asking price on average. Condo buyers, at 2.1 months and 96% of list, have more room to negotiate. The water constraint matters most for the single-family side, because single-family homes are part of what Union Point is expected to add, and those are the homes that can't arrive until the infrastructure does.

The only other nearby new building with a firm date is small. The Patriot Ledger reported in September that a 42-apartment building under construction in Lower Jackson Square, on Commercial Street, is slated to open in the first quarter of 2027.

A Few Questions That Come Up

Does "pre-sold" mean 2,500 households have bought homes at Union Point? The reporting doesn't say that. It's the developer's own combined figure across multifamily, single-family, townhome, and over-55 housing. It comes with no names of builders, no prices, and no move-in dates, so it's safest to read it as committed demand for development parcels.

Could Union Point grow faster before the MWRA pipeline opens? On the Weymouth side, the published limit is the 450,000 gallons per day the town has allocated. On the Abington side, the developers are pursuing the Brockton water memorandum and local well improvements to get started earlier. Neither report gives a timeline for either option.

Is Shea Memorial Grove affected by the road work? The new road is planned to curve behind the Grove's jet display. The Grove itself is a free, one-acre town park with an A-4 Skyhawk, memorials, and walkways, open dawn to dusk with limited parking. None of the reports we reviewed announced a closure or detour there. The developers' promised project website is where schedule updates are supposed to be posted.

If you're deciding between a Weymouth single-family home now and waiting to see what Union Point brings, I'm always glad to talk through those timelines over a cup of tea and look at what's actually for sale this month. Angela Bergin has worked the South Shore since 2002. Let's Connect.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.